Shongtong Hydel Project Progresses Rapidly

Date:

Share post:

The 450 MW Shongtong Hydropower Project has achieved significant progress, officials reported at a Cabinet Sub-Committee meeting chaired by Revenue and Tribal Development Minister Jagat Singh Negi.

Himachal Pradesh Power Corporation Limited (HPPCL) updated that the river diversion work has been completed, the barrage construction is nearing completion, and 81.91% of the feeder tunnel has been finished. Hydro-mechanical works have also commenced.

HPPCL Managing Director Abid Hussain Sadiq stated that the first unit of the project is scheduled for commissioning by December 2026. Key milestones already achieved include the widening of three vertical pressure shafts and the completion of Unit-1 of the powerhouse.

Expressing satisfaction with the progress, Minister Negi urged officials to accelerate work on the Lippa project and ensure timely completion of all ongoing hydropower projects.

Jagat Singh Negi Sets Deadline for Land Records

Daily News Bulletin

Nurturing Creativity – Keekli Charitable Trust, Shimla

Related articles

Amarnath Yatra 2026: Early Surge in Devotees

Jammu and Kashmir Chief Secretary Atal Dulloo on Thursday reviewed preparations for the upcoming 57-day Amarnath Yatra at...

India Tightens Anti-Doping Laws, Targets Traffickers

Union Sports Minister Dr. Mansukh Mandaviya on Wednesday said the government is working to introduce criminal provisions against...

Govt Assures Stable Fuel Supply Amid West Asia Tensions

The Government of India on Wednesday said it is closely monitoring developments in West Asia while ensuring smooth...

India Eyes Global Lead in Clean Energy Push

Union Minister Dr. Jitendra Singh said India is emerging as a global player in clean energy through a...