Shongtong Hydel Project Progresses Rapidly

Date:

Share post:

The 450 MW Shongtong Hydropower Project has achieved significant progress, officials reported at a Cabinet Sub-Committee meeting chaired by Revenue and Tribal Development Minister Jagat Singh Negi.

Himachal Pradesh Power Corporation Limited (HPPCL) updated that the river diversion work has been completed, the barrage construction is nearing completion, and 81.91% of the feeder tunnel has been finished. Hydro-mechanical works have also commenced.

HPPCL Managing Director Abid Hussain Sadiq stated that the first unit of the project is scheduled for commissioning by December 2026. Key milestones already achieved include the widening of three vertical pressure shafts and the completion of Unit-1 of the powerhouse.

Expressing satisfaction with the progress, Minister Negi urged officials to accelerate work on the Lippa project and ensure timely completion of all ongoing hydropower projects.

Jagat Singh Negi Sets Deadline for Land Records

Daily News Bulletin

Nurturing Creativity – Keekli Charitable Trust, Shimla

Related articles

Primary Schools Issue: Govt Forms High-Level Panel

The Himachal Pradesh Education Department has set up a high-level committee to review the objections raised by the...

मुंशी प्रेमचंद: कलम से क्रांति तक

डॉ. कमल के. प्यासा - मण्डी उपन्यास सम्राट, समाज सुधारक, नेक एवं कुशल अध्यापक, संपादक, प्रकाशक के साथ-साथ स्वाधीनता...

Shimla’s Sealed Roads Open Up With Lower Fees

The Himachal Pradesh Government has introduced the Shimla Road Users and Pedestrians (Public Safety and Convenience) Amendment Ordinance,...

Himachal Mineral Revenue Jumps 70% in Three Years

CM Sukhu has said that revenue generated from mineral extraction in Himachal Pradesh has increased by 70 percent...