Shongtong Hydel Project Progresses Rapidly

Date:

Share post:

The 450 MW Shongtong Hydropower Project has achieved significant progress, officials reported at a Cabinet Sub-Committee meeting chaired by Revenue and Tribal Development Minister Jagat Singh Negi.

Himachal Pradesh Power Corporation Limited (HPPCL) updated that the river diversion work has been completed, the barrage construction is nearing completion, and 81.91% of the feeder tunnel has been finished. Hydro-mechanical works have also commenced.

HPPCL Managing Director Abid Hussain Sadiq stated that the first unit of the project is scheduled for commissioning by December 2026. Key milestones already achieved include the widening of three vertical pressure shafts and the completion of Unit-1 of the powerhouse.

Expressing satisfaction with the progress, Minister Negi urged officials to accelerate work on the Lippa project and ensure timely completion of all ongoing hydropower projects.

Jagat Singh Negi Sets Deadline for Land Records

Daily News Bulletin

Nurturing Creativity – Keekli Charitable Trust, Shimla

Related articles

This Day in History

1821 Peru Gains IndependenceOn 28 July 1821, Peru officially declared independence from Spanish colonial rule after a historic proclamation...

Today, 28 July, 2026 : World Hepatitis Day and World Nature Conservation Day

World Hepatitis Day and World Nature Conservation Day, observed every year on 28 July, highlight two important global...

Director Of School Education Releases Meri Laghu Kahaniyan

Director of School Education, Himachal Pradesh, Ashish Kohli, on Monday released Meri Laghu Kahaniyan, a collection of short...

IIAS Seminar Revisits Tilak’s Vision of Nationhood

A three-day international seminar on “The Role of Tilak in National Integration” commenced at the Indian Institute of...