Shongtong Hydel Project Progresses Rapidly

Date:

Share post:

The 450 MW Shongtong Hydropower Project has achieved significant progress, officials reported at a Cabinet Sub-Committee meeting chaired by Revenue and Tribal Development Minister Jagat Singh Negi.

Himachal Pradesh Power Corporation Limited (HPPCL) updated that the river diversion work has been completed, the barrage construction is nearing completion, and 81.91% of the feeder tunnel has been finished. Hydro-mechanical works have also commenced.

HPPCL Managing Director Abid Hussain Sadiq stated that the first unit of the project is scheduled for commissioning by December 2026. Key milestones already achieved include the widening of three vertical pressure shafts and the completion of Unit-1 of the powerhouse.

Expressing satisfaction with the progress, Minister Negi urged officials to accelerate work on the Lippa project and ensure timely completion of all ongoing hydropower projects.

Jagat Singh Negi Sets Deadline for Land Records

Daily News Bulletin

Nurturing Creativity – Keekli Charitable Trust, Shimla

Related articles

This Day in History

1970 First Earth Day observed: Millions of people across the United States took part in the inaugural Earth Day,...

Today, 22 April, 2026 : World Earth Day

World Earth Day is observed every year on April 22 to raise global awareness about environmental protection and...

हिमाचल : धातु अभिलेख, संदर्भ मण्डी – डॉ. कमल के. प्यासा

डॉ. कमल के. प्यासा - जीरकपुर, (मोहाली) मण्डी क्षेत्र से प्राप्त होने वाले धातु अभिलेखों में ताम्र पट्ट, धातु...

CM Sukhu targets irregularities in Himcare scheme

Allegations of irregularities in the Himcare health scheme have come under official scrutiny, with Himachal Pradesh Chief Minister...