February 12, 2026

Shongtong Hydel Project Progresses Rapidly

Date:

Share post:

The 450 MW Shongtong Hydropower Project has achieved significant progress, officials reported at a Cabinet Sub-Committee meeting chaired by Revenue and Tribal Development Minister Jagat Singh Negi.

Himachal Pradesh Power Corporation Limited (HPPCL) updated that the river diversion work has been completed, the barrage construction is nearing completion, and 81.91% of the feeder tunnel has been finished. Hydro-mechanical works have also commenced.

HPPCL Managing Director Abid Hussain Sadiq stated that the first unit of the project is scheduled for commissioning by December 2026. Key milestones already achieved include the widening of three vertical pressure shafts and the completion of Unit-1 of the powerhouse.

Expressing satisfaction with the progress, Minister Negi urged officials to accelerate work on the Lippa project and ensure timely completion of all ongoing hydropower projects.

Jagat Singh Negi Sets Deadline for Land Records

Daily News Bulletin

Nurturing Creativity – Keekli Charitable Trust, Shimla

Related articles

Viksit Bharat and Net Zero Strategies Released

NITI Aayog has released eleven study reports outlining scenarios to achieve Viksit Bharat by 2047 while progressing towards...

INSA, CSIR-NIScPR Join Hands for STI Policy Research

The Indian National Science Academy (INSA) and the National Institute of Science Communication and Policy Research (CSIR-NIScPR) signed...

This Day In History

1929 Lateran Treaty: Italy and the Vatican formalized the Lateran Treaty, establishing Vatican City as a sovereign, independent state. 1945 Yalta...

Today, 11 February, 2026 : International Day of Women and Girls in Science & Safer Internet Day

11 February highlights two important initiatives. The International Day of Women and Girls in Science, declared by the...