Shongtong Hydel Project Progresses Rapidly

Date:

Share post:

The 450 MW Shongtong Hydropower Project has achieved significant progress, officials reported at a Cabinet Sub-Committee meeting chaired by Revenue and Tribal Development Minister Jagat Singh Negi.

Himachal Pradesh Power Corporation Limited (HPPCL) updated that the river diversion work has been completed, the barrage construction is nearing completion, and 81.91% of the feeder tunnel has been finished. Hydro-mechanical works have also commenced.

HPPCL Managing Director Abid Hussain Sadiq stated that the first unit of the project is scheduled for commissioning by December 2026. Key milestones already achieved include the widening of three vertical pressure shafts and the completion of Unit-1 of the powerhouse.

Expressing satisfaction with the progress, Minister Negi urged officials to accelerate work on the Lippa project and ensure timely completion of all ongoing hydropower projects.

Jagat Singh Negi Sets Deadline for Land Records

Daily News Bulletin

Nurturing Creativity – Keekli Charitable Trust, Shimla

Related articles

This Day in History

1789 George Washington becomes the first President of the United States, elected unanimously by the Electoral College. 1902 Australia rolls out...

Today, 4 February, 2026 : World Cancer Day

World Cancer Day, observed every year on February 4, is a global initiative led by the Union for...

Nationwide Free Health Check-ups Amid Holi Celebrations

On the fourth day of Janaushadhi Saptah 2026, free health check-up camps were successfully organized across various states...

सीएम आवास पर रंगों की रौनक

सुखविंदर सिंह सुक्खू ने आज अपने सरकारी आवास ओक ओवर में समाज के सभी वर्गों के साथ होली का...